नेपालको पानी जनताको लगानी, हरेक नेपाली विद्युतको शेयरधनी

Government of Nepal

Ministry of Energy, Water Resources and Irrigation

Janatako Jalavidhyut Karyakram

Janatako Jalavidhyut Karyakram

Sanjen (Upper)

Sanjen (Upper) Hydroelectric Project is a run-of-river scheme with daily peaking facility for 1 hour 10 minutes. The whole scheme is divided into three work sites, viz.Headworks Site that covers diversion weir, undersluice, intake, gravel trap, spillway, desanding basin, peaking pond, forabay and pressure conduit, Underground Works that covers headrace tunnel, rocktrap, surge tank, penstock tunnel and construction adits, and Powerhouse Site that covers surface penstock, powerhouse structure, tailrace and switchyard.

The headworks site is located at Tiloche of Chilime VDC. The headworks consist of overflow diversion weir of height 3.3m and one number of undersluice of size 3m wide and 3m high, side intake structure of 12m long, gravel trap of size 25 m long and 4.2 m wide, dufour type double chamber surface desander basin of size 60m long, 8.5 m wide and 6 m deep, peaking pond of size 138 m long and 65 m wide, forebay and 30m long low pressure conduit connecting to the headrace tunnel portal.

Headrace tunnel is 1378m long, inverted D shape of excavated section 3.5m x 3.75m and will be partly unlined, partly shotcrete lined and partly concrete lined. Surge tank is simple cylindrical type of height 40m and diameter 6m. Penstock is 478m long and mostly exposed type. Surface powerhouse is located at Simbu Village of Chilime VDC. Powerhouse will accommodate three units of horizontal axis Francis turbines of capacity 5.1 MW each and three units of 3-phase synchronous AC generators of capacity 5.85 MVA each. Three numbers of tailrace canals each of 5 m long will discharge the tail water to the Forebay/Intake of Sanjen Hydroelectric Project (SHEP). Surface switchyard is located adjacent to the powerhouse complex.

Generated power from Sanjen (Upper) Hydroelectric Project will be evacuated through a 5km long 132 kV single circuit transmission line to connect from SUHEP powerhouse to the proposed Chilime Hub of NEA and then to the national grid via 220 kV double circuit line up to Trishuli 3B hub of NEA.

Salient Features

Location Chilime V.D.C. of Rasuwa district.
Developer Sanjen Hydropower Company Limited
Type of Project Peaking Run-Of-River
Hydrology  
Catchment area (Dam site) 180 km2
90% dependable flow 2.4 m3/s
Design flow  (Q40) 11.07 m3/s
Design flood (Q100) 194 m3/s
   
Geology  
Rock Type: Medium grade metamorphosed schist and quartzite
   
Head  
Gross 161.30 m
Net 156.0m
   
Headworks  
Weir 14 m (l) x 3.30 m (h)
Undersluice Single Bay 3.0 m wide
Intake Type Side Intake
Intake Size 2 Nos, 5.50 m (w) x 1.40 m (h)
Desanding Basin  
Type Surface Dufour Type Double Chambre
Size 60 m (l) x 8.5 m (w) x 7.13 m (h)
   
Peaking Pondage  
Gross Storage Capacity 40,000 m3
Normal Water Level 2347.55 m
   
Headrace Tunnel  
Length  1386.00 m
Section  3.50 m (w) x 3.75 m (h)  : D- shaped
   
Surge Tank  
Type Simple Cylindrical
Size  40.00 m (h), 6 m (dia)
   
Penstock  
Type Underground
Size  500 m (l), 1.1~2.5 m (dia)
   
Powerhouse  
Type Surface
Size  46.60 m (l) x 12.00 m (b), 20.00 m (h)
Tailrace 30 m (l) x 3 m (b) x 5 m (h)
Turbine  
Type Francis, Horizontal Axis
Capacity 3 Nos., 5.1 MW each
   
Generator  
Type 3 Phase Synchronous AC
Rated Power 3 Nos., 5.85 MVA each
Installed Capacity 14.8 MW
   
Annual Energy Generation 85.87 GWh
Dry Months Energy 11.02 GWh
Wet Months Energy 74.85 GWh
   
Salable Energy 82.439 GWh
Dry Month Energy 10.58 GWh
Wet Month Energy 71.85 GWh
   
Transmission Line  
Length 5 km
Voltage 132 kV